OPENING OF BIDS FOR THE CONSTRUCTION OF THE PIPELINE, NÉSTOR KIRCHNER

Energy Argentina today gave a fundamental step in the framework of the project Pipeline, as President Néstor Kirchner to perform the receipt and opening of bids for its construction.

This is the Public Tender GPNK 07/2022 “Engineering, procurement of equipment and materials, construction – Pipeline President Néstor Kirchner and additional works Stage I”.

It received bids of the companies: BTU; TECHINT-SACDE; ESUCO; TGS AND CONTRERAS BROTHERS-VICTOR CONTRERAS

The event was attended by the virtual participation of the Minister of Economy, Silvina Batakis, and the Secretary of Energy, Darío Martínez, what made in person to the assistant Secretary of Electric Power Federico Basualdo, the President of Energy Argentina, Augustine Gerez, and the Deputy general manager, Gaston Leydet.

The minister Silvina Batakis, said: “expanding our energy capacity is critical for unlocking the productive activity of the country, and we are working with all sectors”.

Then, the secretary Dario Martinez said that “this work will position to Argentina on a path to greater energy security, with the possibility of having activity of gas in all the provinces, replacing imports and save foreign exchange, but also get many industrial parks have the possibility of having gas, that many argentine and argentine in each of our provinces have a gas at a price because it will allow us to access more energy to competitive values, promoting the production and the work, as well as the replacement of gas imports, and exporting to the region and the world.”

In this instance it was the opening of the one with the history of the various bidders, which will be analyzed, and then, between those who comply with the requirements established in the specifications, proceed to the opening of the envelope 2 with the financial bid.

The Pipeline, as President Néstor Kirchner, who form part of the Programme Transport.Ar, you will need an extension of 573 miles between the town neuquén of Tratayén and Salliqueló, in the west of the province of Buenos Aires, crossing the Rio Negro and La Pampa. The project also includes additional works such as the gas pipeline Mercedes-Cardales and the loop of the pipeline NEUBA II, totalling well 680 kilometres of pipes in Stage I.

It should be noted that on 16 June, it signed the contract with the company SIAT for the provision of pipes 36 and 30 inches.

The Pipeline, as President Néstor Kirchner will allow us to extend a 25% of the system's ability to transport natural gas from argentina. In addition it will be critical to the development of production in Vaca Muerta, as it will allow the input arrives to the major consumption centers of the country, improving its entirety, the behavior of the gas transportation system.

Also present were directors of Energy Argentina Oscar Cretini, María Belén Santos, Victor Bronstein, Mariano Barrier and Mario Metaza. competitive.”

For his part, the President of Energy Argentina, Augustine Gerez, stressed that the pipeline “is the great work of transformation for the future of our country because it will allow us to access more energy to competitive values, promoting the production and work, as well as the replacement of gas imports, and exporting to the region and the world.”

In this instance it was the opening of the one with the history of the various bidders, which will be analyzed, and then, between those who comply with the requirements established in the specifications, proceed to the opening of the envelope 2 with the financial bid.

The Pipeline, as President Néstor Kirchner, who form part of the Programme Transport.Ar, you will need an extension of 573 miles between the town neuquén of Tratayén and Salliqueló, in the west of the province of Buenos Aires, crossing the Rio Negro and La Pampa. The project also includes additional works such as the gas pipeline Mercedes-Cardales and the loop of the pipeline NEUBA II, totalling well 680 kilometres of pipes in Stage I.

It should be noted that on 16 June, it signed the contract with the company SIAT for the provision of pipes 36 and 30 inches.

The Pipeline, as President Néstor Kirchner will allow us to extend a 25% of the system's ability to transport natural gas from argentina. In addition it will be critical to the development of production in Vaca Muerta, as it will allow the input arrives to the major consumption centers of the country, improving its entirety, the behavior of the gas transportation system.

Also present were directors of Energy Argentina Oscar Cretini, María Belén Santos, Victor Bronstein, Mariano Barrier and Mario Metaza.

News related

Fifth Public LNG Tender

Energía Argentina has issued its fifth Request for Proposal (RFP) of the year for the supply of Liquefied Natural Gas (LNG). Proposals are requested for seven delivery dates, from which the volumes required by market demand will be selected.

Naturgy Awarded One LNG Cargo Supply Contract

Luego de la Licitación Abierta Internacional realizada el pasado 15 de abril, Energía Argentina adjudicó a la empresa Naturgy Aprovisionamientos S.A un cargamento de Gas Natural Licuado (GNL).

Two Bids Compete for LNG Commercialization Under the New Supply Scheme

Energía Argentina has received two technical bids as part of National and International Public Tender No. 01/2026 for the selection of a Commercializer-Aggregator agent for Liquefied Natural Gas (LNG). Comercializador-Agregador de Gas Natural Licuado (GNL).

International tender to select a supplier–aggregator of LNG

We launched the Public procurement National and International levels for the selection of an agent marketer–aggregator for the acquisition of Liquefied Natural Gas (LNG) and its commercialization in the domestic market nationwide during the winter period.
The process aims to select an operator that is in charge of importing LNG and market it as a gas regasificado in the domestic market, through the use of the regasification terminal located in Escobar.

According to the reactivation of the works of the dams on the Santa Cruz river

Energía Argentina reached an agreement for the resolution of historical conflicts with the Transient Binding (UT) contractor of the work, a necessary step to move forward in the wake of the works of the Hydro power stations in the Santa Cruz River.

Invitation to Tender National and International Public for the sale of shares of Citelec

The National Undersecretariat of Electric Energy has announced the launch of a National and International Public Tender for the sale of shares in Compañía Inversora en Transmisión Eléctrica S.A. (CITELEC).

Menu