Energy Argentina continues to make important steps in the bidding process for the construction of the Pipeline, as President Néstor Kirchner.
The President of Energy Argentina, Augustine Gerez, and the deputy general manager, Gaston Leydet, led the opening of the envelope number two in the Line 3, which corresponds to the construction of 133 kilometers of pipe that extends between the kilometer 440 of the trace, in the province of la Pampa, and Salliqueló in the province of Buenos Aires, at the end of the path, the backbone of the pipeline.
In this opportunity, the offer is supported technically to the line 3 was the BTU SA.
On the other hand, and then the opening of financial offers made yesterday, the UTE TECHINT-SACDE was awarded the Line 2. Present were directors of Energy Argentina Victor Bronstein and Mario Metaza.